Lost Creek Presbyterian Church (U.S.A.)
CalendarMinistryPrayerHistory
YouthAbout UsContact UsHome
Sketch of Fire Damage Inside the Church

UPDATES - JUNE


 

MAKING PLANS FOR A NEW ROOF

April and May were relatively slow months here at Lost Creek Presbyterian Church.  The general contractor, W.S. Miller, was carefully taking measurements for the roof trusses.  One aspect of the sanctuary that made this difficult was that the four corners of the building were not even.  They wanted to make sure the trusses would fit the roof line yet line up evenly when installed.

The steel floor joistThey were also concerned about taking out the timbers from the old roof.  All the timbers were interconnected and they didn't want to cut out one timber and have other timbers cave in.  W.S. Miller hired Gates Timber Frames to remove the timbers.  This company specializes in building timber frame homes.  This time they were tearing the framing down.

While this planning was taking place the work crew was busy installing a steel floor joist and pole that would support the interior corner of a new, steel bell tower.  They also prepared the steel I-beams that would form the bottom of the bell tower and would support the front 7 roof trusses.


 

RAZING THE ROOF

In June things got very busy around the church.  The crew from Gates Timber Frames shored up the brick walls.  Even though Scott, the owner of Gates Timber Frames, believed the walls were Removing the old roofing materialsstrong enough to stand on their own, no one wanted to take any chances that the walls might be damaged during the re-roofing.  So they took the extra step of shoring up the walls before removing the roof.  The lumber will also serve as studs for the new walls inside the sanctuary.

On June 7 my family went on a trip to Pittsburgh for a week where I attended a pastor's seminar.  When we came back, we turned the corner onto Main street, and there was NO roof on the church.  While we were gone W.S. Miller had removed all the roofing materials, leaving just the timber frame in place.  It was a shock!  Thanks to Ron Knouse for documenting with photos the removal of the roof while we were gone.

The Timber Frame of the Old RoofThe timbers revealed an interesting history of the construction of the church.  There were two roof lines.  A lower, interior roof line was formed by 4 very heavy trusses.  According to Scott the grooves on the trusses were only a foot apart suggesting that these trusses had once supported a slate roof.  However, the pitch was not steep enough and the weight of the roof had bowed the trusses.  So the old roof was removed and the trusses were used to support a second, higher slate roof.  The timbers for this second roof were made from tree trunks that were split in half and put in place without any further carpentry work.  It took Gates Timber Frame about a week to remove the old roof timbers.

Pictures of the crews removing the old roof

Pictures of removing an old truss


 

RAISING THE ROOF

With all vestiges of the  old roof completely removed, W.S. Miller laid cinder blocks on top of the brick walls to form a bonding strip for the new roof trusses.  Many of the blocks had to be Half the new trusses in placetrimmed so that when the bonding strip was completed the walls would be level between the 4 uneven corners of the building.  They also installed the steel I-beams on which the front trusses would sit.

Recently the Roberts Brothers 3 Ring Circus came to town.  It set up in the field right behind our church.  The last act was a man riding a motorcycle on a high wire with a woman sitting on a trapeze below the motor cycle.  It was an amazing stunt.  Here at the end of June we're watching another high wire act as the crew from W.S. Miller installs the new roof trusses.  The crane lifts each truss in place while several men scurry about on nothing but 2x6's nailing the truss in place and connecting it to other trusses.

Pictures of the preparation for the new roof

Pictures of lifting a truss into place

 

Back to the Rebuilding Page